Status: Approval
25 BRENTFORD CLOSE HAYES UB4 9QG
Conversion of integral garage to habitable accommodation, erection of a single storey extension to the rear, amendments to fenestration.
4 GREENCROFT AVENUE RUISLIP
Conversion of roof space to habitable use to include a rear dormer, 2 x front roof lights and conversion of roof from hip to gable end with new gable end window (Application for a Certificate of Lawful Development for a Proposed Development)
UNIT D Prologis Park STOCKLEY ROAD WEST DRAYTON UB7 9FN
Details pursuant to the discharge of Conditions 10 (Details of Chiller Plant) and 11 (Details of Generator Plant) as attached to planning permission reference 18399/APP/2025/16 dated 01-09-2025 (An application submitted under Section 73 of the Town and Country Planning Act 1990 to vary Conditions 2 (Approved Drawings) and 3 (Compliance with supporting documentation) of planning permission reference 18399/APP/2022/411, dated 03-05-2023 (Installation of plant and equipment to unit DC6 including external plant equipment, external louvres and associated security fencing and landscaping, to facilitate use of the building as a data centre) to make changes to the design of the development.).
15 DRAKES DRIVE NORTHWOOD
Changing flat roof to pitch roof to the front extension and garage, replacing garage door with a window, creating entrance porch, insulating and rendering external walls (Amendments to Planning Permission Ref: 32191/APP/2025/347, dated 11-04-25, Erection of single storey front and rear extensions and first floor side extension)
12 LAVENDER ROAD HILLINGDON
Conversion of roof space to habitable use to include rear dormer, 2x front roof lights, Juliette balcony to rear, and erection of outbuilding to rear garden (certificate of lawful development)
1 PRIORY CLOSE RUISLIP
Details pursuant to the discharge of Condition 3 (Replacement Window Details) of planning permission ref. 56257/APP/2022/3336, dated 06-01-2025 (Replacement of front and rear windows and tree removal.)
50 REGINALD ROAD NORTHWOOD
Conversion of roof space to habitable use to include a rear dormer/outrigger side dormer, 1 x front rooflight, 1 x flat roof rear rooflight and removal of existing chimney (Application for a Certificate of Lawful Development for a Proposed Development)
Land at Bulls Bridge Industrial Estate NORTH HYDE GARDENS HAYES UB3 4QQ
Details pursuant to the partial discharge of Conditions 31 (Contaminated Land), 34 (EA - Verification Report) and 38 (EA - Decommissioning of Boreholes) in relation to Data Centre Blocks 2 and 3 (UP2 and UP3) only as attached to planning permission ref. 75111/APP/2020/1955 dated 15-04-2021 (Site clearance and preparation, including the demolition of remaining buildings, and the redevelopment of the site to provide: a new data centre (Use Class B8), two MV Energy Centres (including stand-by generation plant and gas storage), a HV Sub-Station, a visitor reception centre, plant, the creation of a new footpath and cycleway link to the canal towpath, works to the highway, car parking, cycle parking, associated infrastructure, enclosures and necessary physical security systems, hard and soft landscaping (including works to the River Crane) and ancillary uses, as well as associated external works).
Land at Bulls Bridge Industrial Estate NORTH HYDE GARDENS HAYES UB3 4QQ
Details pursuant to the partial discharge of Conditions 28 (Contaminated Land), 30 (EA - Verification Report) and 34 (EA - Decommissioning of Boreholes) in relation to Energy Centre Blocks 2 and 3 (EC2 and EC3) and Visitor Reception Centre 2 (VRC2) only as attached to planning permission ref. 5111/APP/2022/1007 dated 21-09-2022 (Full planning permission for site clearance and preparation, including the demolition of remaining buildings, and the redevelopment of the site to provide three energy centres, two visitor reception centres, a new footpath and cycleway link to the canal towpath, works to the highway, car parking, cycle parking, associated infrastructure, enclosures and necessary physical security systems, hard and soft landscaping, and ancillary uses, as well as associated external works).
Land at Bulls Bridge Industrial Estate NORTH HYDE GARDENS HAYES UB3 4QQ
Details pursuant to the discharge of Condition 41 (District Heating Strategy) as attached to planning permission ref. 75111/APP/2020/1955 dated 15-04-2021 (Site clearance and preparation, including the demolition of remaining buildings, and the redevelopment of the site to provide: a new data centre (Use Class B8), two MV Energy Centres (including stand-by generation plant and gas storage), a HV Sub-Station, a visitor reception centre, plant, the creation of a new footpath and cycleway link to the canal towpath, works to the highway, car parking, cycle parking, associated infrastructure, enclosures and necessary physical security systems, hard and soft landscaping (including works to the River Crane) and ancillary uses, as well as associated external works).
Land at Bulls Bridge Industrial Estate NORTH HYDE GARDENS HAYES UB3 4QQ
Details pursuant to the discharge of Condition 36 (District Heating Strategy) as attached to planning permission ref. 5111/APP/2022/1007 dated 21-09-2022 (Full planning permission for site clearance and preparation, including the demolition of remaining buildings, and the redevelopment of the site to provide three energy centres, two visitor reception centres, a new footpath and cycleway link to the canal towpath, works to the highway, car parking, cycle parking, associated infrastructure, enclosures and necessary physical security systems, hard and soft landscaping, and ancillary uses, as well as associated external works).
35 MIDHURST GARDENS HILLINGDON
Details pursuant to the discharge of Conditions 5 (Landscaping), 6 (Construction Management Plan), 7 (Step Free Access), 8 (Sustainable Water Management) and 9 (Biodiversity Net Gain Plan) of planning permission ref. 79103/APP/2025/666, dated 12-05-2025 (Erection of a 2-bedroom, 3-person dwelling with private amenity space , refuse area and car parking. Erection of a first-floor extension to the rear and loft conversion including hip to gable extension, rear dormer and front rooflights to the existing dwelling (amended description)).
9 MANSFIELD DRIVE HAYES UB4 8DZ
Erection of a single storey rear extension (Application for a Certificate of Lawful Development for a Proposed Development)
12A BEDFORD AVENUE HAYES
Conversion of roofs pace to habitable use to include rear dormer, 3 x front roof lights, erection of front porch, and erection of outbuilding to rear garden. (Application for a Certificate of Lawful Development for a Proposed Development)
RUISLIP RUGBY FOOTBALL CLUB WEST END ROAD RUISLIP
Details pursuant to the discharge of Conditions 3 (Materials) and 4 (Landscaping) of planning permission ref. 6440/APP/2023/2382 dated 12-04-2024 (Erection of single storey extensions to existing changing rooms to both the side (north) and the rear (west). Erection of a pitched roof over the existing flat roof to the changing areas. Installation of an external servery hatch and 2 no. doors to the rear elevation. Fenestration changes).
51 PEMBROKE ROAD RUISLIP HA4 8NQ
Erection of two storey side and rear extensions, conversion of roof space to habitable use to include the alteration of the roof profile, insertion of 4 rear and 3 front roof lights. Conversion of dwelling house into 2 x 2-bed and 2 x 1-bed self-contained flats with associated parking and amenity space.