LAND AT HARVIL ROAD HAREFIELD
Proposal:
HS2 request for approval of Plans and Specifications under condition imposed by Schedule 17 to the High Speed Rail (London - West Midlands) Act 2017, relating to the Harvil Road Realignment Works, covering a site area of 46,528.5m2, including the Harvil Road Stream Underbridge (comprising wingwalls, parapets, box culvert and mammal ledge); earthworks associated with the highway embankments, access roads to the realigned Harvil Road, and the location of vehicle restraint systems and fencing; building works associated with the concrete weir and non-woven geotextile bags at the attenuation pond; earthworks associated with the attenuation pond area comprising swales, gabion baskets, access road; pedestrian access track; an attenuation pond and the location of fencing.
| Status | Approval |
| Ward | Ickenham & South Harefield |
| Case Officer | Karl Dafe |
| Received | 14th Oct 2022 |
| Validated | 18th Oct 2022 |
| Target Decision | 22nd Feb 2023 |
| Decided Date | 29th Mar 2023 |