Leisure Centre Refurbishment Programme 2023/24 - Botwell Green Sports & Leisure Centre Refurbishment Works - RELEASE NO: 2
Report Document
Can't see the PDF? Download Report
Decision / Minutes Document
Can't see the PDF? Download Minutes
Text extracted from PDFs
View Report Text
Democratic Services Location: Phase II Ext: 0693 DDI: 01895 250693 CMD No: 877 To: COUNCILLOR MARTIN GODDARD CABINET MEMBER FOR FINANCE COUNCILLOR EDDIE LAVERY CABINET MEMBER FOR RESIDENTS’ SERVICES c.c. All Members of th e Residents’ Services Select Committee c.c. Nicky McDermott – Place Directorate c.c. Perry Scott – Corporate Director of Place Date: 10 August 2023 Non-Key Decision request Form D CAPITAL RELEASE REPORT (August 2023) DEPARTMENT: Place SERVICE AREA / PROGRAMME: Leisure Centre Refurbishment Programme 2023/24 - Botwell Green Sports & Leisure Centre Refurbishment Works RELEASE NO: 2 Dear Cabinet Members Attached is a report requesting that a decision be made by you as an individual Cabinet Member. Democratic Services confirm that this is not a key decision, as such, the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012 notice period does not apply. You should take a decision on or after Friday 18 August 2023 in order to meet Constitutional requirements about publication of decisions that are to be made. You may wish to discuss the report with the Corporate Director before it is made. Please indicate your decision on the duplicate memo supplied, and return it to me when you have made your decision. I will then arrange for the formal notice of decision to be published. Steve Clarke Democratic Services Officer Title of Report: Leisure Centre Refurbishment Programme 2023/24 - Botwell Green Sports & Leisure Centre Refurbishment Works – Release No 2 Decision made: Reasons for your decision: (e.g. as stated in report) Alternatives considered and rejected: (e.g. as stated in report) Signed ……………………………………………………… Date……………………. Cabinet Member for Residents’ Services / Cabinet Member for Finance Cabinet Member Report – 10 August 2023 Page 1 Part 1 - Public CAPITAL RELEASE REPORT (August 2023) DEPARTMENT: Place SERVICE AREA / PROGRAMME: Leisure Centre Refurbishment Programme 2023/24 - Botwell Green Sports & Leisure Centre Refurbishment Works RELEASE NO: 2 Cabinet Members Councillor Eddie Lavery Councillor Martin Goddard Cabinet Portfolios Cabinet Member for Residents Services Cabinet Member for Finance Officer Contact Nicky McDermott – Place Directorate Papers with report Appendix A - Capital Release Requests for Approval HEADLINES Summary To seek Cabinet Member approval for the release of capital funds. Putting our Residents First Delivering on the Council Strategy 2022-2026 This report supports our ambition for residents / the Council of: Live active and healthy lives. This report supports our commitments to residents of: Thriving, Healthy Households . Financial Cost This report seeks the release of £ 549,894 from the Leisure Centre Refurbishment Programme capital budget to carry out the works required to Botwell Green Sports & Leisure Centre. The works will commence upon release of the funds and are due for completion by October 2023. Relevant Select Committee Residents’ Services Select Committee Relevant Ward(s) Hayes Town RECOMMENDATION That the Cabinet Member for Residents ’ Services and Cabinet Member for Finance agree to the capital release request of £ 549,894 from the Leisure Centre Refurbishment Programme 2023/24 capital budget to carry out the refurbishment works to Botwell Green Sports and Leisure Centre (Appendix A). Cabinet Member Report – 10 August 2023 Page 2 Part 1 - Public Reasons for recommendation Completing this work will improve the health and fitness facilities at Botwell Green Sports and Leisure Centre, thus benefitting Hillingdon residents. It will enable the facilities to continue to be competitive in the local area and ensure that they remain financially viable to the Council. Alternative options considered The Council could choose not to complete the work , but this could result in a facility that is not financially viable and at risk of service failures as well damage to the Council’s reputation. Select Committee comments None at this stage. SUPPORTING INFORMATION The Council’s four Leisure Centres (Hillingdon Sports & Leisure Complex, Highgrove Pool, Botwell Green Sports & Leisure Centre and Queensmead Sports Centre) are managed by GLL on behalf of the Council. The Leisure Management contract, which commenced in February 2020, included a comprehensive capital investment programme designed to ensure the centres continued to meet the needs and demands of residents, both now and in the future, and balance the needs of the facilities with expected financial return, service improvements and increased usage. The capital developments were initially planned for 2020/21 and 2021/22 but were delayed due to the Covid- 19 pandemic. The delivery of the Botwell Green Sports and Leisure Centre project is the last of these schemes and will ensure the long-term viability of the leisure centre as well as offering Hillingdon residents a first-class leisure service. The project will comprise of the following elements: • New gym equipment and functional kit at Botwell Green Sports & Leisure Centre • Building and refurbishment works to the gym and the swimming pool changing village • Reception and access control upgrade to improve the customer experience and to protect income generated at Botwell • L ED lighting features for the health and fitness areas This report now seeks the release of the funds from the Leisure Centre Refurbishment Budget in order for GLL to complete the works on behalf of the Council. The cost breakdown can be found in Table 1 overleaf: Cabinet Member Report – 10 August 2023 Page 3 Part 1 - Public Table 1: Cost Plan Description £ New gym equipment and functional kit 137,337 Building and refurbishment works to the gym and swimming pool changing village 340,482 Reception and access control upgrade 64,075 LED lighting features 8,000 Total 549,894 Financial Implications Leisure Centre Refurbishment Programme Budget 2023/24 £900k, Previously Released £128k, Capital Release Requested £550k – Appendix A The 2023/24 capital programme, approved by Cabinet and Council in February 2023, included a budget for the Leisure Centre Refurbishment Programme of £100k funded from Council resources. In June 2023, Cabinet approved the rephasing of £800k unspent funds from 2022/23 into 2023/24, of which £62k had previously been released for schemes completing this year. The report seeks the release of £550 k from the Leisure Centre Refurbishment Programme for refurbishment works to Botwell Green Sports & Leisure Centre. The release request is based on quotes from the Council’s approved term contractor GLL. It is anticipated that the re furbishment works will increase usage and income generated. The remaining £222k of the Leisure Centre Refurbishment 2023/24 budget is subject to the capital release process. RESIDENT BENEFIT & CONSULTATION The benefit or impact upon residents, service users and communities The completion of these refurbishment works will ensure that residents will continue to be able to enjoy a high-quality leisure centre provision. Consultation carried out or required None required. CORPORATE CONSIDERATIONS Corporate Finance Corporate Finance has reviewed the report and concurs with the financial implications set out above, noting that the funds are to be released from the approved 2023/24 Leisure Centre Refurbishment capital budget financed from Council resources. Cabinet Member Report – 10 August 2023 Page 4 Part 1 - Public Legal Legal Services confirms that the Council is responsible for carrying out this function pursuant to section 19 of the Local Government (Miscellaneous Provisions) Act 1976 . Thus, there are no legal impediments to the capital release being authorised, although any contract that is entered into must comply with the Council's Procurement and Contract Standing Orders. Capital Release Protocol The release of all capital funds, and certain revenue funds, held by the Council is to be made by a formal democratic decision. No expenditure can be placed or committed by officers until this formal approval is given by Democratic Services. Release of funds must be for identified projects only and strictly not for the general release of funds for projects to be identified at a later date. No block releases of capital or funding will be allowed, except if authorised by the Leader of the Council in advance to Corporate Finance. The release of funds will only be made if previous Council, Cabinet or Cabinet Member agreement has been given to the project and only if there is an approved budget. BACKGROUND PAPERS NIL. Cabinet Member Report – 10 August 2023 Page 5 Part 1 - Public APPENDIX A – CAPITAL REALEASE REQUEST FOR APPROVAL Leisure Centre Refurbishment Programme 2023/24: Botwell Green Sports & Leisure Centre (Release No 2) Location Project / Expenditure Title Information Funds Release Sought £000s Approve Hold More Information Required Botwell Green Sports & Leisure Centre Specialist refurbishment works Health and fitness gym development, changing room development, reception upgrade 550 Total seeking release 550 Previously released 128 Budget 900 Remaining budget 222
View Decision / Minutes Text
Executive Decision Notice – 07 September 2023 Page 1
This notice is a public document also available to view on the Council's website www.hillingdon.gov.uk
OFFICIAL EXECUTIVE DECISION NOTICE
PUBLISHED BY DEMOCRATIC SERVICES
Notice is hereby given that the following decision(s) have been made today by
Cabinet Members at the London Borough of Hillingdon:
Title of decision
CAPITAL RELEASE REPORT (August 2023)
DEPARTMENT: Place
SERVICE AREA / PROGRAMME: Leisure Centre
Refurbishment Programme 2023/24 - Botwell Green Sports &
Leisure Centre Refurbishment Works
RELEASE NO: 2
Reference No. 877
Date of decision Thursday 07 September 2023
Call-in expiry date Thursday 14 September 2023
Relevant Select
Committee
Residents’ Services Select Committee
Relevant Wards Hayes Town
Decision made
Cabinet Members
making the decision
Councillor Martin Goddard – Cabinet Member for Finance
Councillor Eddie Lavery – Cabinet Member for Residents ’
Services
Decision Approved
That the Cabinet Member for Residents’ Services and
Cabinet Member for Finance agreed to the capital release
request of £549,894 from the Leisure Centre Refurbishment
Programme 2023/24 capital budget to carry out the
refurbishment works to Botwell Green Sports and Leisure
Centre.
Reason for decision Completing this work will improve the health and fitness facilities
at Botwell Green Sports and Leisure Centre, thus benefitting
Hillingdon residents. It will enable the facilities to continue to be
competitive in the local area and ensure that they remain
financially viable to the Council.
Alternative options
considered and
rejected
The Cabinet Members could have chosen not to complete the
work, but this w ould have resulted in a facility that wa s not
financially viable and at risk of service failures as well damage
to the Council’s reputation.
Classification Part I – Public
Link to associated
report
Here
Relevant Officer
contacts &
Directorate
Nicky McDermott – Place Directorate
Executive Decision Notice – 07 September 2023 Page 2
This notice is a public document also available to view on the Council's website www.hillingdon.gov.uk
Any interest declared
by the Cabinet
Member(s) /
dispensation granted
N/A
Implementation of decision & scrutiny call-in
[Internal Use only]
When can this
decision be
implemented by
officers?
Officers can implement Cabinet Member decision in this notice
only from the expiry of the scrutiny call-in period which is:
5pm on Thursday 14 September 2023
However, this is subject to the decision not being called in by
Councillors on the relevant Select Committee. Upon receipt of a
valid call-in request, Democratic Services will immediately advise
the relevant officer(s) and the decision must then be put on hold.
Councillor scrutiny
call-in of this
decision
Councillors on the relevant Select Committee shown in this notice
may request to c all-in this decision. The request must be before
the expiry of the scrutiny call-in period above.
Councillors should use the Scrutiny Call -in App (link below) on
their devices to initiate any call-in request. Further advice can be
sought from Democratic Services if required:
Scrutiny Call-In - Power Apps (secure)
Further information These decisions, where applicable, have been taken under The
Local Authorities (Executive Arrangements) (Meetings and
Access to Information) (England) Regulations 2012.
This is the formal notice by the Council of the above executive
decision, including links to the reports where applicable.
If you would like more information on this decision, please contact
Democratic Services on 01895 250636 or email:
democratic@hillingdon.gov.uk.
Circulation of this decision notice is to a variety of people including
Members of the Council, Corporate Directors, Officers, Group
Secretariats and the Public. Copies are also placed on the
Council’s website.
Democratic Services
London Borough of Hillingdon
Civic Centre
High Street
Uxbridge
UB8 1UW