Executive Decision Notice – 13 October 2023 Page 1
This notice is a public document also available to view on the Council's website www.hillingdon.gov.uk
OFFICIAL EXECUTIVE DECISION NOTICE
PUBLISHED BY DEMOCRATIC SERVICES
Notice is hereby given that the following decision(s) have been made today by
Cabinet Members at the London Borough of Hillingdon:
Title of decision
VARIATION TO PRE -CONSTRUCTION AND
PROFESSIONAL SERVICES CONTRACTS WITH CAPITAL
RELEASE FOR EXPANSION OF MEADOW HIGH SCHOOL
(FORMER HAREFIELD ACADEMY BOARDING BLOCK
SITE)
Reference No. 917
Date of decision Fiday 13 October 2023
Call-in expiry date Friday 20 October 2023
Relevant Select
Committee
Property, Highways and Transport Select Committee
Relevant Wards Colham & Cowley and Harefield Village
Decision made
Cabinet
Members
making the
decision
Councillor Ian Edwards – Leader of the Council
Councillor Jonathan Bianco – Cabinet Member for Property, Highways
and Transport
Councillor Martin Goddard – Cabinet Member for Finance
Approved
That the Leader of the Council, the Cabinet Member for Property,
Highways and Transport and the Cabinet Member for Finance:
1. A pproved the variation to the Pre-Construction Services
Agreement (PCSA) with ISG Limited for the design, early
works orders and procurement of work packages, to
achieve an overall fixed price cost to enter a JCT Design &
Build Contract for a new academic building in the former
Harefield Academy (Northwood Road, Harefield) boarding
block for the use as a satellite provision for Meadow High
School, noting that t his is part of the overall expansion of
Meadow High School and the variation cost to the PCSA is
£615,681;
2. Approved the further appointment of Pellings LLP on the
London Borough of Hillingdon F ramework – Lot 1 , to
provide multi-disciplinary services for RIBA Stages 2 & 3
and 5 & 6 through the PCSA two-stage tender process, for
the replacement of the former boarding block with a n ew
academic building as described within the report under
change of works proposals, noting the cost is £283,300;
Executive Decision Notice – 13 October 2023 Page 2
This notice is a public document also available to view on the Council's website www.hillingdon.gov.uk
3. Approved the early procurement and installation of two
temporary modular classrooms for the academic year 2024-
2025 that are to be placed at Meadow High School (Royal
Lane, Uxbridge), noting officers’ estimated cost of £280,000
to lease the modular classrooms;
4. Approved the procurement of new electricity supply/
substation and sprinkler water supply , noting o fficers
estimated cost of £200,000 to include all connection and
associated costs;
5. Agreed to the capital release request of £1,553,313 from the
Schools SRP Programme budget for the services and
works outlined in the above recommendation; and
6. Noted that officers are continuing discussions with the DfE
on capital funding for the Safety Valve Agreement.
Reason for
decision
Approval of the appointment ensures the increasing need for Special
School places for pupils with Moderate Learning Difficulties and Autism
(MLD and ASD) can be provided within the Borough. This project was
one of the Devolved School Grant (DSG) Deficit Recovery Plan projects
outlined to Cabinet in April 2022.
Alternative
options
considered
and rejected
Not progressing with this proposed scheme w ould have increased the
use of expensive independent Special School places. A single stage
tender process was also considered; however, the current market had no
appetite for single stage and to reduce the risk of no replies, a two-stage
process was undertaken.
Classification Part 2
Link to
associated
report
That this report be declared as exempt from publication as it
involves the disclosure of information in accordance with Section
100(A) and paragrap h 3 of Part 1 of Schedule 12 (A) to the Local
Government Act 1972 (as amended), in that the report contains
information relating to the financial or business affairs of any
particular person (including the authority holding that information)
and that the p
ublic interest in withholding the information
outweighs the public interest in disclosing it.
Relevant
Officer
contact &
Directorate
Tim Martin – Place Directorate
Any interest
declared by
the Cabinet
Member(s) /
dispensation
granted
N/A
Executive Decision Notice – 13 October 2023 Page 3
This notice is a public document also available to view on the Council's website www.hillingdon.gov.uk
Implementation of decision & scrutiny call-in
[Internal Use only]
When can this
decision be
implemented by
officers?
Officers can implement Cabinet Member decision in this notice
only from the expiry of the scrutiny call-in period which is:
This decision comes into effect at 5pm on Friday 20 October
2023.
However, this is subject to the decision not being called in by
Councillors on the relevant Select Committee. Upon receipt of a
valid call-in request, Democratic Services will immediately advise
the relevant officer(s) and the decision must then be put on hold.
Councillor scrutiny
call-in of this
decision
Councillors on the relevant Select Committee shown in this
notice may request to call-in this decision. The request must be
before the expiry of the scrutiny call-in period above.
Councillors should use the Scrutiny Call-in App (link below) on
their devices to initiate any call-in request. Further advice can be
sought from Democratic Services if required:
Scrutiny Call-In - Power Apps (secure)
Further information These decisions, where applicable, have been taken under The
Local Authorities (Executive Arrangements) (Meetings and
Access to Information) (England) Regulations 2012.
This is the formal notice by the Council of the above executive
decision, including links to the reports where applicable.
If you would like more information on this decision, please
contact Democratic Services on 01895 250636 or email:
democratic@hillingdon.gov.uk.
Circulation of this decision notice is to a variety of people
including Members of the Council, Corporate Directors, Officers,
Group Secretariats and the Public. Copies are also placed on
the Council’s website.
Democratic Services
London Borough of Hillingdon
Civic Centre
High Street
Uxbridge
UB8 1UW